Re: What did you get done? 11/05
Worked on the "garagemahal" all weekend. Prepared the floor to pour concrete this week. Made sure the base gravel was flat and and the slab averaged 5 inches thick throughout. Put down moisture barrier and wire mesh. Also installed the meter base and electrical panel and wired them together along with a few outlets and lights. Commercial power should arrive this week also. I am about 30 days behind schedule but atleast I will have power and a floor before "true" Atlanta winter arrives (rain, more rain, cold rain, ice and then some more rain) In the words of Forest Gump..."one day it started raining.....and it didnt stop"
|